Sec.  263.18  Program completion-time objectives.

    To provide a Program responsive to local needs, the following target 
(maximum) completion time objectives are established and should be used 
to the extent feasible, in scheduling work and programming funds. 
Shortening of these objectives is encouraged for specific studies and 
projects when appropriate. However, high standards of planning, design 
and construction are not to be sacrificed. Attainment of completion-time 
objectives through intensive management is to be a major concern for 
those elements and individuals given Program management responsibilities 
in Sec.  263.16 of this regulation.

             Program Authorities, Completion Times in Months
------------------------------------------------------------------------
                                       205, 107,               Emergency
                                       103, and   208 and 14   14 and 3
                                          111                     \1\
------------------------------------------------------------------------
(a) Completion of recon and                    2           1           2
 submission of funding request or
 negative report to OCE.............
(b) Completion of feasibility study           16           9      (\2\ )
 by reporting officer and
 preparation of DPR.................
(c) Review of DPR or recon report by           2           1          .5
 division engineer, (including
 provisions of Sec.   263.15(f))....
(d) Review of DPR or recon report by           2           1          .5
 OCE................................
(e) Completion of project                     18          12           3
 construction (including plans and
 specifications), after project
 approval...........................
                                     -----------------------------------
(f) Total completion-time objective.          40          24           6
------------------------------------------------------------------------
\1\ The decision to utilize a recon report or DPR for recommending a
  project under sec. 14 authority is delegated to the division engineer
  (Sec.   263.17(b)(3)).
\2\ Not applicable.