[Code of Federal Regulations]
[Title 33, Volume 3]
[Revised as of July 1, 2007]
From the U.S. Government Printing Office via GPO Access
[CITE: 33CFR263.27]

[Page 361-366]
 
                TITLE 33--NAVIGATION AND NAVIGABLE WATERS
 
 CHAPTER II--CORPS OF ENGINEERS, DEPARTMENT OF THE ARMY, DEPARTMENT OF 
                                 DEFENSE
 
PART 263_CONTINUING AUTHORITIES PROGRAMS--Table of Contents
 
                    Subpart D_Shore Protection Policy
 
Sec.  263.27  Authority for mitigation of shore damage attributable to 

navigation works (Section 111).

    (a) Legislative authority. Section 111 of the River and Harbor Act 
of 1968 (Pub. L. 90-483, approved August 13, 1968) states:

    The Secretary of the Army, acting through the Chief of Engineers is 
authorized to investigate, study, and construct projects for the 
prevention or mitigation of shore damages attributable to Federal 
navigation works. The cost of installing, operation and maintaining 
shall be borne entirely by the United States. No such projects shall be 
constructed without specific authorization by Congress if the estimated 
first cost exceeds $1,000,000.

    (b) Definitions--(1) Federal navigation works is defined as a 
project or feature thereof that has been specifically authorized by the 
Congress in a River and

[[Page 362]]

Harbor Act or authorized under the continuing authorities granted by 
section 201 or the Flood Control Act of 1965, or by section 107 of the 
River and Harbor Act of 1960, as amended. These shall include projects 
or project features built by others but which have been adopted as a 
Federal Navigation project.
    (2) Beach erosion control project is defined as a project that has 
been specifically authorized by the Congress in a River and Harbor Act 
or authorized under the continuing authorities granted by section 201 of 
the Flood Control Act of 1965 or by section 103 of the River and Harbor 
Act of 1962. This is considered to include the beach erosion control 
portion of combined beach erosion and hurricane protection projects.
    (3) Mitigation of shore damages is defined as the construction of 
works or procedures to reduce erosion-type damages by shoreline 
stabilization. The degree of mitigation is the reduction of erosion or 
accretion to the level which would be obtained without the influence of 
navigation works at the time navigation works were accepted as a Federal 
responsibility. It is not intended that shorelines be restored to 
historic dimensions, but only to lessen the damages by an action that 
can be justified, the entire costs of which are Federal regardless of 
shore ownership.
    (c) General policies. (1) This Act authorizes the study, 
construction and maintenance of work for prevention or mitigation of 
damages to both public and privately owned shores to the extent of the 
damages that can be directly identified and attributed to Federal 
navigation work located along the coastal and Great Lakes shorelines of 
the United States. This authority will not be used:
    (i) For construction of works for prevention or mitigation of shore 
damages such as those caused by river bank erosion or vessel generated 
wave wash.
    (ii) To modify navigation projects authorized, but not constructed, 
that contain features for prevention or mitigation of shore damages or 
to change the responsibility for maintenance or to modify portions of 
constructed navigation projects that contain features for prevention or 
mitigation of shore damages.
    (iii) For prevention or mitigation of shore damages caused by non-
Federal navigation projects.
    (iv) To construct, maintain, modify or change the cost sharing of 
authorized beach erosion or combined beach erosion and hurricane 
protection projects, or portions thereof, located adjacent to Federal 
navigation projects. Except, when it is determined that shore damage to 
a portion of an authorized beach erosion project is attributable to the 
navigation project, mitigation measures may be accomplished under this 
authority, only to the extent of damages that can be directly identified 
and attributed to the navigation project.
    (2) Where the erosion attributable to the Federal navigation project 
consists of only a portion of the total erosion problem in a specific 
area and cannot be considered as a separable reach for effective 
mitigation measures then a section 111 project cannot be considered for 
authorization unless,
    (i) There is an authorized beach erosion control or combined beach 
and hurricane protection project for the area with which the section 111 
mitigation measures could be combined to become effective, or
    (ii) A general study of the entire problem area is made and leads to 
the development of an authorized beach erosion control project, 
(specific authority must be obtained to conduct a general study of the 
entire problem area) or
    (iii) Local interests indicate a willingness to have the erosion 
problem outside the scope of section 111 remedied at local cost.
    (d) Cost limitations. Section 111 provides that the Chief of 
Engineers has authority to authorize projects for which the estimated 
first costs will not exceed $1,000,000. The first costs will be the cost 
of the initial preventive or mitigative measures only. The limitation on 
costs does not include the cost of project maintenance. The project must 
be planned as a complete unit and not broken into reaches or stages for 
cost limitation purposes.
    (e) Reports. The Recon Report required by Sec.  263.15(c)(1) will:

[[Page 363]]

    (1) Determine whether or not Federal navigation works are 
responsible for causing or contributing to the erosion problem.
    (2) Determine the extent of the area affected by the navigation 
works.
    (3) Determine total area experiencing significant erosion.
    (4) Determine the approximate percentage of the total erosion 
problem in a specific area that is attributable to the navigation works.
    (5) Recommend whether further study of the specific area affected by 
the Federal navigation works is justified and whether study of the 
entire area is desirable.
    (f) Evaluation of mitigation measures. The objective of section 111 
is to provide mitigation measures for shore damages attributable to 
Federal navigation projects, when equitable and in the public interest. 
All practicable alternatives, structural and non-structural should be 
identified and considered. Work recommended for construction should 
provide the most practicable and economical means of mitigating existing 
damages or the prevention of subsequent damages. Justification of 
mitigation measures should be made by comparing their costs with the 
values represented by the damages preventable. Any intangible values 
should be described and given due weight along with the tangible values 
in this justification. Exercise of the authority of section 111 to 
provide mitigation measures at Federal expense is not mandatory. A 
finding for or against its use should fully consider the pre-project 
conditions and the justification of incurring mitigation costs.
    (g) Criteria for a Favorable Recommendation. A recommendation 
favorable to adoption and construction of work to prevent or mitigate 
shore damage attributable to a Federal navigation project under the 
authority of section 111 of the River and Harbor Act of 1968 may be 
considered warranted when both of the following conditions exist:
    (1) The navigation project has been determined to be the cause of 
the damage.
    (2) Analysis based on sound engineering and economic principles 
clearly demonstrates the feasibility of the proposed work.
    (h) Cost sharing--(1) Construction. (i) If the work recommended in 
the report is confined to mitigation work only under section 111, i.e., 
erosion totally attributable to the navigation works, costs will be 100 
percent Federal.
    (ii) If the work recommended is a combination of mitigation under 
section 111 and restoration of beaches eroded due to other causes and 
there is no authorized beach erosion project, mitigation work under 
section 111 will be 100 percent Federal and the remaining work will be 
100 percent local.
    (iii) If the work recommended in the report is a combination of 
mitigation under section 111 and the restoration of beaches under an 
authorized beach erosion project or combination beach erosion-hurricane 
protection project, the mitigation work under section 111 will be 100 
percent Federal and the remainder in accordance with the cost sharing 
procedures as specified in project authorization documents.
    (2) Maintenance. (i) If the initial work is confined to mitigation 
under section 111, all maintenance costs are 100 percent Federal.
    (ii) If the work is a combination of mitigation under section 111 
and restoration of beaches eroded due to other causes, and there is no 
authorized beach erosion project, maintenance costs will be shared in 
the same proportion as recommended for initial construction, i.e., the 
section 111 portion will be 100 percent Federal and remaining work 100 
percent local.
    (iii) If the work is a combination of mitigation under section 111 
and an authorized beach erosion control project or combination beach 
erosion-hurricane protection project, the Federal maintenance cost for 
the mitigation work under section 111 will be in the same proportion as 
the damage attributed to the Federal navigation work is to the total 
damage. For the remaining work the cost sharing procedures of the 
authorized beach erosion or combined beach erosion-hurricane protection 
project will apply.
    (i) Local cooperation. (1) The law as written provided that the cost 
of installing, operating and maintaining projects under this authority 
shall be

[[Page 364]]

borne entirely by the United States; therefore there are no requirements 
for local cooperation. The cost of any lands, easements or rights-of-way 
required for construction or subsequent maintenance will be borne 
entirely by the United States.
    (2) Where section 111 projects are to be accomplished in conjunction 
with other works (Sec.  263.15(a)(2)) local interests will be required 
to furnish assurance of local cooperation similar to those required for 
regularly authorized projects for their assigned portion of the work.
    (3) Where section 111 projects are to be accomplished in conjunction 
with authorized projects, the requirements of local cooperation 
specified in the authorizing document or report will apply.

   Appendix A to Part 263--History of Program and Project Limitations 
                     Continuing Authorities Program

----------------------------------------------------------------------------------------------------------------
                                                                                       Federal cost     Annual
                Section/law                             Date               Public law   limitation     program
                                                                              No.       per project     limit
----------------------------------------------------------------------------------------------------------------
                                                    (1) Small Flood Control Project Authority (Sec. 205)
                                           ---------------------------------------------------------------------
Sec. 205 of 1948 FCA......................  June 30, 1948...............       80-858      $100,000   $2,000,000
Sec. 212 of 1950 FCA......................  May 17, 1950................       81-516       150,000    3,000,000
Public Law 685/84th Congress, 2d Sess.....  July 11, 1956...............       84-685       400,000   10,000,000
Sec. 205 of 1962 FCA......................  Oct. 23, 1962...............       87-874     1,000,000   25,000,000
Sec. 61 of WRDA of 1974...................  Mar. 7, 1974................       93-251           \1\   30,000,000
                                                                                          1,000,000
                                                                                                \3\
                                                                                          2,000,000
Sec. 133(6) WRDA of 1976..................  Oct. 22, 1976...............       94-587     2,000,000   30,000,000
                                                                                                \3\
                                                                                          3,000,000
                                           ---------------------------------------------------------------------
                                            (2) Authority for Snagging and Clearing for Flood Control (Sec. 208)
                                           ---------------------------------------------------------------------
Sec. 2 of 1937 FCA........................  Aug. 28, 1937...............       75-406       $25,000     $300,000
Sec. 13 of 1946 FCA.......................  July 24, 1946...............       79-526        50,000    1,000,000
Sec. 208 of 1954 FCA......................  Sept. 3, 1954...............       83-780       100,000    2,000,000
Sec. 26 of WRDA of 1974...................  Mar. 7, 1974................       93-251       250,000    5,000,000
                                           ---------------------------------------------------------------------
                                             (3) Authority for Emergency Streambank and Shoreline Protection of
                                                     Public Works and Nonprofit Public Services (Sec. 14)
                                           ---------------------------------------------------------------------
Sec. 14 of 1946 FCA.......................  July 24, 1946...............       79-526       $50,000   $1,000,000
Sec. 27 of WRDA of 1974...................  Mar. 7, 1974................       93-251       250,000   10,000,000
----------------------------------------------------------------------------------------------------------------
                                                      (4) Small Navigation Project Authority (Sec. 107)
                                           ---------------------------------------------------------------------
Sec. 107 of 1960 R. & H. Act..............  July 14, 1960...............       86-645      $200,000   $2,000,000
Sec. 310 of 1965 R. & H. Act..............  Oct. 27, 1965...............       89-298       500,000   10,000,000
Sec. 112 of 1970 R. & H. Act..............  Dec. 31, 1970...............       91-611     1,000,000   25,000,000
Sec. 133(a) of WRDA of 1976...............  Oct. 22, 1976...............       94-587     2,000,000   25,000,000
                                           ---------------------------------------------------------------------
                                               (5) Authority for Snagging and Clearing for Navigation (Sec. 3)
                                           ---------------------------------------------------------------------
Sec. 3 of 1945 R. & H. Act................  Mar. 2, 1945................        79-14          None     $300,000
                                           ---------------------------------------------------------------------
                                                (6) Small Beach Erosion Control Project Authority (Sec. 103)
                                           ---------------------------------------------------------------------
Sec. 103 of 1962 R. & H. Act..............  Oct. 23, 1962...............       87-874      $400,000   $3,000,000
Sec. 310 of 1965 R. & H. Act..............  Oct. 27, 1965...............       89-298       500,000   10,000,000
Sec. 112 of 1970 R. & H. Act..............  Dec. 31, 1970...............       91-611     1,000,000   25,000,000
                                           ---------------------------------------------------------------------
                                                (7) Authority for Mitigation of Shore Damages Attributable to
                                                                Navigation Projects (Sec. 111)
                                           ---------------------------------------------------------------------
Sec. 111 of 1968 R. & H. Act..............  Aug. 13, 1968...............       90-483           \2\         None
                                                                                         $1,000,000
----------------------------------------------------------------------------------------------------------------
\1\ Project cost may go to $2,000,000 if project is located in a major disaster area designated by the
  President.
\2\ A project exceeding $1 million will be transmitted to Congress for specific authorization.
\3\ Federal cost may go to higher amount if project is located in a major disaster area designated by the
  President.


[40 FR 51134, Nov. 3, 1975, as amended at 41 FR 56943, Dec. 30, 1976]

[[Page 365]]

Appendix B to Part 263--Application of Multiobjective Planning Framework 
                    to Continuing Authorities Program

    1. General. The planning process described in the ER 1105-2-200 
series of regulations including the implementation of Federal planning 
and evaluation criteria, are generally applicable to studies conducted 
under the Continuing Authorities Program. However, due to the limited 
scope of many of the plans and projects considered under this program, 
modification of the process is appropriate. Specific modification of the 
requirements of the planning criteria is not appropriate since the 
legislative and executive authorities setting forth these criteria do 
not differentiate between various types of level C implementation 
studies. Discretion must be employed by reporting officers and reviewers 
of Detailed Project Reports to insure that projects recommended for 
implementation by the Corps have been selected on the basis of 
information and analyses consistent with the WRC Principles and 
Standards, while at the same time keeping the requirements for 
information and analyses consistent with the scope of the study, 
solutions recommended, and the Program completion-time objectives 
outlined in Sec.  263.18 of this regulation.
    2. Plan Formulation Stages.
    a. Stage 1--Reconnaissance Study (Recon). As presented in para. 6c, 
a Reconnaissance will replace the Development of a Plan of Study as the 
primary element of Stage 1 planning. As a general rule, a Recon should 
be conducted by a study team consisting of an engineer, an economist, 
and an environmentalist. A one-to-two day field reconnaissance should be 
sufficient to analyze the need for a project, to develop sketch plans, 
discuss views and capabilities of local interests, and identify the 
economy of the potential project area and possible environmental issues 
that would need to be addressed if a feasibility study were to be 
conducted. Additional effort should pinpoint all data deficiencies, 
types of investigations required for the feasibility study, and the 
estimated cost of the study. The latter identification process can be 
developed as a Plan of Study for the feasibility study, if approved and 
funded. To accomplish the intended purpose of the Recon, within the time 
and cost objectives given in this regulation, reporting officers are not 
required to develop a specific project (except for emergency situations 
under Section 14 or 3 Authorities), but should only provide the 
information required to make a decision as to whether there is a Federal 
interest in conducting a feasibility study. Mature, seasoned judgment is 
a prime requisite.
    b. Stage 2--Development of Alternative Plans. While the ER 1105-2-
200 series of regulations provides for a three-stage development of 
plans, studies under Continuing Authorities may consolidate these two 
final stages (intermediate and detailed), into a single stage, if 
appropriate. This consolidation does not eliminate any of the planning 
tasks, as discussed in para 3 below, nor does it diminish the concept of 
screening a full array of alternatives including nonstructural measures, 
with increasing levels of detail in the assessment of impacts and 
evaluation as planning progresses to plan selection. The primary 
emphasis in making the consolidation of these two stages is that the 
plan selection is normally made on the basis of more limited data and 
analyses than appropriate for studies conducted under the Level C Survey 
Program or the Phase I AE&D Program.
    c. Stage 3--Development of Recommended Plan. The feasibility study 
under the Continuing Authorities Program will include the design of a 
recommended plan to the extent necessary to proceed directly from the 
Detailed Project Report to preparation of plans and specifications. 
While studies under the Level C Survey Program would complete plan 
formulation prior to accomplishing detailed project design, the nature 
of this Program necessitates a flexible design phase, wherein changes in 
scope of the selected plan, with accompanying changes in project impacts 
and evaluation, are to be expected and handled by planning personnel in 
order that the DPR will reflect a selected plan consistent with 
completed detailed design and a plan justified under the current Federal 
evaluation criteria for recommending Federal participation.
    3. Planning Tasks.
    a. Problem Identification. While planning under Continuing 
Authorities is to be on a multi-objective basis, the range of problems 
that can be addressed under a particular Program authority is more 
limited than normally considered in the conduct of studies specifically 
authorized by Congress. A good effort to focus the study on relevant 
problems should be made in the Recon phase of the study, while more 
intense efforts at data collection and definition of the problems and 
associated needs should be accomplished during Stage 2 planning.
    b. Formulation of Alternatives. There are no fundamental differences 
in the process of formulating alternatives under these Program 
authorities than in Level C Survey studies, with the exception that the 
array of alternatives will normally be more limited based on the 
discussion in para 3a above. The level of detail to which the 
alternatives are formulated, with associated assessments of impacts and 
evaluation of beneficial and adverse contributions, will vary greatly 
depending on the study authority. In some cases, alternatives will be 
screened and eliminated for various reasons without full development of 
a tentative plan which can be

[[Page 366]]

assessed and evaluated. Such screening is consistent with the nature of 
this Program; however, good judgment and interdisciplinary participation 
should be emphasized in such preliminary screenings. The guidance in the 
ER 1105-2-200 series of regulations with regard to consideration of non-
structural measures and formulation of NED and EQ plans, is fully 
applicable to studies conducted under this Program.
    c. Impact Assessment. There is no difference in the requirements for 
the assessment of impacts for studies conducted under Continuing 
Authorities and those under the Level C Survey Program. As in all 
studies, the extent to which information is obtained to adequately 
assess impacts of alternative plans is a matter of discretion of the 
reporting officer, bearing in mind the requirements of the National 
Environmental Policy Act of 1969 (NEPA) and Section 122, Public Law 91-
611.
    d. Evaluation. The processes, analyses and displays for evaluation 
of alternative plans as prescribed in the ER 1105-2-200 series of 
regulations are generally applicable to studies conducted under 
Continuing Authorities. Again, the level of detail, and not the process 
itself, is to be consistent with the study authority and the needs of 
the decision-making process.