Sec.  385.21  Quality control.

    (a) The Corps of Engineers and the non-Federal sponsor shall prepare 
a quality control plan, in accordance with applicable Corps of Engineers 
regulations, for each product that will be produced by a Project 
Delivery Team. The quality control plan shall be included in the Project 
Management Plan and shall describe the procedures to be used to ensure 
compliance with technical and policy requirements during implementation.
    (b) During development of the Project Management Plan for each 
project, the Corps of Engineers and the non-Federal sponsor shall 
establish a Technical Review Team to conduct reviews to ensure that 
products are consistent with established criteria, guidance, procedures, 
and policy. The members of the Technical Review Team

[[Page 633]]

shall be independent of the Project Delivery Team and the project being 
reviewed, and should be knowledgeable of design criteria established for 
the Plan.
    (c) Technical review is intended to be a continuous process 
throughout project implementation. The Technical Review Team shall 
document its actions and recommendations and provide reports to the 
Project Delivery Team at designated points during the implementation 
process that shall be described in the quality control plan.