Sec.  385.24  Project Management Plans.

    (a) General requirements. (1) The Corps of Engineers and the non-
Federal sponsor shall, in consultation with the Department of the 
Interior, the Environmental Protection Agency, the Department of 
Commerce, the Seminole Tribe of Florida, the Miccosukee Tribe of Indians 
of Florida, the Florida Department of Environmental Protection, and 
other Federal, State, and local agencies, develop a Project Management

[[Page 635]]

Plan prior to initiating activities on a project.
    (2) The Project Management Plan shall define the activities, and 
where appropriate, the subordinate tasks, as well as the assignment of 
responsibility for completing products and activities such as Project 
Implementation Reports, Pilot Project Design Reports, plans and 
specifications, real estate acquisition, construction contracts and 
construction, Comprehensive Plan Modification Reports, and other 
activities necessary to support implementation of the Plan.
    (3) The Project Management Plan shall include a quality control 
plan, as described in Sec.  385.21.
    (4) As appropriate, the Project Management Plan shall include 
activities to be conducted to meet the requirements of the Fish and 
Wildlife Coordination Act, as described in Sec.  385.26(e).
    (5) The Project Management Plan shall provide schedule and funding 
information for the project.
    (6) In accordance with Sec.  385.18, Corps of Engineers and the non-
Federal sponsor shall provide opportunities for the public to review and 
comment on the Project Management Plan.
    (b) Revisions to Project Management Plans. The Corps of Engineers 
and the non-Federal sponsor may, in consultation with the Department of 
the Interior, the Environmental Protection Agency, the Department of 
Commerce, the Seminole Tribe of Florida, the Miccosukee Tribe of Indians 
of Florida, the Florida Department of Environmental Protection, and 
other Federal, State, and local agencies, revise the Project Management 
Plan whenever necessary, including after completion of the Project 
Implementation Report, or Plans and Specifications. In accordance with 
Sec.  385.18, the Corps of Engineers and the non-Federal sponsor shall 
provide opportunities for the public to review and comment on revisions 
to the Project Management Plan.