    (a) The date of completion of permanent road construction 
obligations as set forth in the Notice of Sale shall be incorporated 
into the timber sale contract.
    (b) This date is applicable to construction by both the Forest 
Service and the timber purchaser.
    (c) The date is not applicable to roads not needed by the purchaser 
for timber removal.
    (d) The date for completion may be revised, if additional time is 
needed, under guidelines provided by the Chief, Forest Service, 
including but not limited to (1) default of contractors or (2) design 
changes, physical changes, or catastrophic damages which necessitate 
modification of specified road construction work.
    (e) If Forest Service failure to perform results in delay in road 
completion, the termination date shall be adjusted in accordance with 
the contract term adjustment provisions of the timber sale contract. If 
there is substantial delay in performance by the Forest Service, the 
contract shall provide that rates of payment may be redetermined, at the 
request of the purchaser, in accordance with guidelines established by 
the Chief, Forest Service.
    (f) If the purchaser retains responsibility for road construction, 
the date of completion for permanent roads may be modified to conform to 
the approved plan of operation.