    (a) Early public notice. If a facility action at the contending 
site(s) could require construction in a wetland, public notice must be 
provided.
    (b) Finding of no practicable alternative. The Postal Service shall 
avoid construction located in a wetland unless it issues a finding of no 
practicable alternative. The facilities organization, in conjunction 
with the operations organization, or, for projects within the delegated 
authority of the Vice President, Area Operations, the operations 
organization, shall make a written determination that:
    (1) There is no practicable alternative to such construction; and
    (2) The proposed action includes all practicable measures to 
minimize harm to wetlands.
    (c) NEPA coordination. If either an Environmental Impact Statement 
or an Environmental Assessment is required under the Postal Service's 
National Environmental Policy Act (NEPA) regulations, the above review 