Sec.  125.87  As an owner or operator of a new facility, must I perform monitoring?

    As an owner or operator of a new facility, you will be required to 
perform monitoring to demonstrate your compliance with the requirements 
specified in Sec.  125.84.
    (a) Biological monitoring. You must monitor both impingement and 
entrainment of the commercial, recreational, and forage base fish and 
shellfish species identified in either the Source Water Baseline 
Biological Characterization data required by 40 CFR 122.21(r)(3) or the 
Comprehensive Demonstration Study required by Sec.  125.86(c)(2), 
depending on whether you chose to comply with Track I or Track II. The 
monitoring methods used must be consistent with those used for the 
Source Water Baseline Biological Characterization data required in 40 
CFR 122.21(r)(3) or the Comprehensive Demonstration Study required by 
Sec.  125.86(c)(2). You must follow the monitoring frequencies 
identified below for at least two (2) years after the initial permit 
issuance. After that time, the Director may approve a request for less 
frequent sampling in the remaining years of the permit term and when the 
permit is reissued, if supporting data show that less frequent 
monitoring would still allow for the detection of any seasonal and daily 
variations in the species and numbers of individuals that are impinged 
or entrained.
    (1) Impingement sampling. You must collect samples to monitor 
impingement rates (simple enumeration) for each species over a 24-hour 
period and no less than once per month when the cooling water intake 
structure is in operation.
    (2) Entrainment sampling. You must collect samples to monitor 
entrainment rates (simple enumeration) for each species over a 24-hour 
period and no less than biweekly during the primary period of 
reproduction, larval recruitment, and peak abundance identified during 
the Source Water Baseline Biological Characterization required by 40 CFR 
122.21(r)(3) or the Comprehensive Demonstration Study required in Sec.  
125.86(c)(2). You must collect samples only when the cooling water 
intake structure is in operation.
    (b) Velocity monitoring. If your facility uses surface intake screen 
systems, you must monitor head loss across the screens and correlate the 
measured value with the design intake velocity. The head loss across the 
intake screen must be measured at the minimum ambient source water 
surface elevation (best professional judgment based on available 
hydrological data). The maximum head loss across the screen for each 
cooling water intake structure must be used to determine compliance with 
the velocity requirement in

[[Page 345]]

Sec.  125.84(b)(2) or (c)(1). If your facility uses devices other than 
surface intake screens, you must monitor velocity at the point of entry 
through the device. You must monitor head loss or velocity during 
initial facility startup, and thereafter, at the frequency specified in 
your NPDES permit, but no less than once per quarter.
    (c) Visual or remote inspections. You must either conduct visual 
inspections or employ remote monitoring devices during the period the 
cooling water intake structure is in operation. You must conduct visual 
inspections at least weekly to ensure that any design and construction 
technologies required in Sec.  125.84(b)(4) and (5), or (c)(3) and (4) 
are maintained and operated to ensure that they will continue to 
function as designed. Alternatively, you must inspect via remote 
monitoring devices to ensure that the impingement and entrainment 