[Code of Federal Regulations]
[Title 40, Volume 21]
[Revised as of July 1, 2007]
From the U.S. Government Printing Office via GPO Access
[CITE: 40CFR125.98]

[Page 360-364]
 
                   TITLE 40--PROTECTION OF ENVIRONMENT
 
         CHAPTER I--ENVIRONMENTAL PROTECTION AGENCY (CONTINUED)
 
PART 125_CRITERIA AND STANDARDS FOR THE NATIONAL POLLUTANT DISCHARGE
ELIMINATION SYSTEM--Table of Contents
 
Subpart J_Requirements Applicable to Cooling Water Intake Structures for 
      Phase II Existing Facilities Under Section 316(b) of the Act
 
Sec.  125.98  As the Director, what must I do to comply with the requirements of this subpart?

    (a) Permit application. As the Director, you must review materials 
submitted by the applicant under 40 CFR 122.21(r) and Sec.  125.95 
before each permit renewal or reissuance.
    (1) You must review and comment on the Proposal for Information 
Collection submitted by the facility in accordance with Sec.  
125.95(a)(1). You are encouraged to provide comments expeditiously so 
that the permit applicant can make responsive modifications to its 
information gathering activities. If

[[Page 361]]

a facility submits a request in accordance with Sec.  125.95(a)(2)(ii) 
for an alternate schedule for submitting the information required in 
Sec.  125.95, you must approve a schedule that is as expeditious as 
practicable, but does not extend beyond January 7, 2008. If a facility 
submits a request in accordance with Sec.  125.95(a)(3) to reduce the 
information about their cooling water intake structures and the source 
waterbody required to be submitted in their permit application (other 
than with the first permit application after September 7, 2004), you 
must approve the request within 60 days if conditions at the facility 
and in the waterbody remain substantially unchanged since the previous 
application.
    (2) After receiving the permit application from the owner or 
operator of a Phase II existing facility, you must determine which of 
the requirements specified in Sec.  125.94 apply to the facility. In 
addition, you must review materials to determine compliance with the 
applicable requirements.
    (3) At each permit renewal, you must review the application 
materials and monitoring data to determine whether new or revised 
requirements for design and construction technologies, operational 
measures, or restoration measures should be included in the permit to 
meet the applicable performance standards in Sec.  125.94(b) or 
alternative site-specific requirements established pursuant to Sec.  
125.94(a)(5).
    (b) Permitting requirements. Section 316(b) requirements are 
implemented for a facility through an NPDES permit. As the Director, you 
must consider the information submitted by the Phase II existing 
facility in its permit application, and determine the appropriate 
requirements and conditions to include in the permit based on the 
compliance alternatives in Sec.  125.94(a). The following requirements 
must be included in each permit:
    (1) Cooling water intake structure requirements. The permit 
conditions must include the requirements that implement the applicable 
provisions of Sec.  125.94. You must evaluate the performance of the 
design and construction technologies, operational measures, and/or 
restoration measures proposed and implemented by the facility and 
require additional or different design and construction technologies, 
operational measure, and/or restoration measures, and/or improved 
operation and maintenance of existing technologies and measures, if 
needed to meet the applicable performance standards, restoration 
requirements, or alternative site-specific requirements. In determining 
compliance with the performance standards for facilities proposing to 
increase withdrawals of cooling water from a lake (other than a Great 
Lake) or a reservoir in Sec.  125.94(b)(3), you must consider 
anthropogenic factors (those not considered ``natural'') unrelated to 
the Phase II existing facility's cooling water intake structures that 
can influence the occurrence and location of a thermocline. These 
include source water inflows, other water withdrawals, managed water 
uses, wastewater discharges, and flow/level management practices (e.g., 
some reservoirs release water from deeper bottom layers). As the 
Director, you must coordinate with appropriate Federal, State, or Tribal 
fish and wildlife management agencies to determine if any disruption of 
the natural thermal stratification resulting from the proposed increased 
withdrawal of cooling water does not adversely affect the management of 
fisheries. Specifically:
    (i) You must review and approve the Design and Construction 
Technology Plan required in Sec.  125.95(b)(4) to evaluate the 
suitability and feasibility of the design and construction technology 
and/or operational measures proposed to meet the performance standards 
in Sec.  125.94(b) or site-specific requirements developed pursuant to 
Sec.  125.94(a)(5).
    (ii) If the facility proposes restoration measures in accordance 
with Sec.  125.94(c), you must review and approve the Restoration Plan 
required under Sec.  125.95(b)(5) to determine whether the proposed 
measures, alone or in combination with design and construction 
technologies and/or operational measures, will meet the requirements 
under Sec.  125.94(c).
    (iii) In each reissued permit, you must include a condition in the 
permit requiring the facility to reduce impingement mortality and 
entrainment (or to increase fish production, if applicable) commensurate 
with the efficacy

[[Page 362]]

at the facility of the installed design and construction technologies, 
operational measures, and/or restoration measures.
    (iv) If the facility implements design and construction technologies 
and/or operational measures and requests that compliance with the 
requirements in Sec.  125.94 be measured for the first permit term (or 
subsequent permit terms, if applicable) employing the Technology 
Installation and Operation Plan in accordance with Sec.  
125.95(b)(4)(ii), you must review the Technology Installation and 
Operation Plan to ensure it meets the requirements of Sec.  
125.95(b)(4)(ii). If the Technology Installation and Operation Plan 
meets the requirements of Sec.  125.95(b)(4)(ii), you must approve the 
Technology Installation and Operation Plan and require the facility to 
meet the terms of the plan including any revision to the plan that may 
be necessary if applicable performance standards or alternative site-
specific requirements are not being met. If the facility implements 
restoration measures and requests that compliance with the requirements 
in Sec.  125.94 be measured for the first permit term (or subsequent 
permit terms, if applicable) employing a Restoration Plan in accordance 
with Sec.  125.95(b)(5), you must review the Restoration Plan to ensure 
it meets the requirements of Sec.  125.95(b)(5). If the Restoration Plan 
meets the requirements of Sec.  125.95(b)(5), you must approve the plan 
and require the facility to meet the terms of the plan including any 
revision to the plan that may be necessary if applicable performance 
standards or site-specific requirements are not being met. In 
determining whether to approve a Technology Installation and Operation 
Plan or Restoration Plan, you must evaluate whether the design and 
construction technologies, operational measures, and/or restoration 
measures the facility has installed, or proposes to install, can 
reasonably be expected to meet the applicable performance standards in 
Sec.  125.94(b), restoration requirements in Sec.  125.94(c)(2), and/or 
alternative site-specific requirements established pursuant to Sec.  
125.94(a)(5), and whether the Technology Installation and Operation Plan 
and/or Restoration Plan complies with the applicable requirements of 
Sec.  125.95(b). In reviewing the Technology Installation and Operation 
Plan, you must approve any reasonable scheduling provisions that are 
designed to ensure that impacts to energy reliability and supply are 
minimized, in accordance with Sec.  125.95(b)(4)(ii)(A). If the facility 
does not request that compliance with the requirements in Sec.  125.94 
be measured employing a Technology Installation and Operation Plan and/
or Restoration Plan, or the facility has not been in compliance with the 
terms of its current Technology Installation and Operation Plan and/or 
Restoration Plan during the preceding permit term, you must require the 
facility to comply with the applicable performance standards in Sec.  
125.94(b), restoration requirement in Sec.  125.94(c)(2), and/or 
alternative site-specific requirements developed pursuant to Sec.  
125.94(a)(5). In considering a permit application, you must review the 
performance of the design and construction technologies, operational 
measures, and/or restoration measures implemented and require additional 
or different design and construction technologies, operational measures, 
and/or restoration measures, and/or improved operation and maintenance 
of existing technologies and measures, if needed to meet the applicable 
performance standards, restoration requirements, and/or alternative 
site-specific requirements.
    (v) You must review and approve the proposed Verification Monitoring 
Plan submitted under Sec.  125.95(b)(7) (for design and construction 
technologies) and/or monitoring provisions of the Restoration Plan 
submitted under Sec.  125.95(b)(5)(v) and require that the monitoring 
continue for a sufficient period of time to demonstrate whether the 
design and construction technology, operational measures, and/or 
restoration measures meet the applicable performance standards in Sec.  
125.94(b), restoration requirements in 125.94(c)(2) and/or site-specific 
requirements established pursuant to Sec.  125.94(a)(5).
    (vi) If a facility requests requirements based on a site-specific 
determination of best technology available for minimizing adverse 
environmental impact, you must review the application materials 
submitted under

[[Page 363]]

Sec.  125.95(b)(6) and any other information you may have, including 
quantitative and qualitative benefits, that would be relevant to a 
determination of whether alternative requirements are appropriate for 
the facility. If a facility submits a study to support entrainment 
survival at the facility, you must review and approve the results of 
that study. If you determine that alternative requirements are 
appropriate, you must make a site-specific determination of best 
technology available for minimizing adverse environmental impact in 
accordance with Sec.  125.94(a)(5). You, as the Director, may request 
revisions to the information submitted by the facility in accordance 
with Sec.  125.95(b)(6) if it does not provide an adequate basis for you 
to make this determination. Any alternative site-specific requirements 
established based on new and/or existing design and construction 
technologies, operational measures, and/or restoration measures, must 
achieve an efficacy that is, in your judgement, as close as practicable 
to the applicable performance standards of Sec.  125.94(b) without 
resulting in costs that are significantly greater than the costs 
considered by the Administrator for a like facility in establishing the 
applicable performance standards in Sec.  125.94(b), determined in 
accordance with Sec.  125.94(a)(5)(i)(A) through (F), or the benefits of 
complying with the applicable performance standards at the facility; and
    (vii) You must review the proposed methods for assessing success in 
meeting applicable performance standards and/or restoration requirements 
submitted by the facility under Sec.  125.95(b)(4)(ii)(D) and/or 
(b)(5)(v)(A), evaluate those and other available methods, and specify 
how assessment of success in meeting the performance standards and/or 
restoration requirements must be determined including the averaging 
period for determining the percent reduction in impingement mortality 
and entrainment and/or the production of fish and shellfish. Compliance 
for facilities who request that compliance be measured employing a 
Technology Installation and Operation Plan and/or Restoration Plan must 
be determined in accordance with Sec.  125.98(b)(1)(iv).
    (2) Monitoring conditions. You must require the facility to perform 
monitoring in accordance with the Technology Installation and Operation 
Plan in Sec.  125.95(b)(4)(ii), the Restoration Plan required by Sec.  
125.95(b)(5), if applicable, and the Verification Monitoring Plan 
required by Sec.  125.95(b)(7). In determining any additional applicable 
monitoring requirements in accordance with Sec.  125.96, you must 
consider the monitoring facility's Verification Monitoring, Technology 
Installation and Operation, and/or Restoration Plans, as appropriate. 
You may modify the monitoring program based on changes in physical or 
biological conditions in the vicinity of the cooling water intake 
structure.
    (3) Recordkeeping and reporting. At a minimum, the permit must 
require the facility to report and keep records specified in Sec.  
125.97.
    (4) Design and construction technology approval--(i) For a facility 
that chooses to demonstrate that it has installed and properly operate 
and maintain a design and construction technology approved in accordance 
with Sec.  125.99, the Director must review and approve the information 
submitted in the Technology Installation and Operation Plan in Sec.  
125.95(b)(4)(ii) and determine if it meets the criteria in Sec.  125.99.
    (ii) If a person requests approval of a technology under Sec.  
125.99(b), the Director must review and approve the information 
submitted and determine its suitability for widespread use at facilities 
with similar site conditions in its jurisdiction with minimal study. As 
the Director, you must evaluate the adequacy of the technology when 
installed in accordance with the required design criteria and site 
conditions to consistently meet the performance standards in Sec.  
125.94. You, as the Director, may only approve a technology following 
public notice and consideration of comment regarding such approval.
    (5) Bi-annual status report. You must specify monitoring data and 
other information to be included in a status report every two years. The 
other information may include operation and maintenance records, 
summaries of adaptive management activities, or any other information 
that is relevant to determining compliance with the

[[Page 364]]

terms of the facility's Technology Operation and Installation Plan and/
or Restoration Plan.