[Code of Federal Regulations] [Title 40, Volume 31] [Revised as of July 1, 2007] From the U.S. Government Printing Office via GPO Access [CITE: 40CFR1506.1] [Page 886-887] TITLE 40--PROTECTION OF ENVIRONMENT CHAPTER V--COUNCIL ON ENVIRONMENTAL QUALITY PART 1506_OTHER REQUIREMENTS OF NEPA--Table of Contents Sec. 1506.1 Limitations on actions during NEPA process. Sec. 1506.1 Limitations on actions during NEPA process. 1506.2 Elimination of duplication with State and local procedures. 1506.3 Adoption. 1506.4 Combining documents. 1506.5 Agency responsibility. 1506.6 Public involvement. 1506.7 Further guidance. 1506.8 Proposals for legislation. 1506.9 Filing requirements. 1506.10 Timing of agency action. 1506.11 Emergencies. 1506.12 Effective date. Authority: NEPA, the Environmental Quality Improvement Act of 1970, as amended (42 U.S.C. 4371 et seq.), Sec. 309 of the Clean Air Act, as amended (42 U.S.C. 7609), and E.O. 11514 (Mar. 5, 1970, as amended by E.O. 11991, May 24, 1977). Source: 43 FR 56000, Nov. 29, 1978, unless otherwise noted. (a) Until an agency issues a record of decision as provided in Sec. 1505.2 (except as provided in paragraph (c) of this section), no action concerning the proposal shall be taken which would: (1) Have an adverse environmental impact; or (2) Limit the choice of reasonable alternatives. (b) If any agency is considering an application from a non-Federal entity, and is aware that the applicant is about to take an action within the agency's jurisdiction that would meet either of the criteria in paragraph (a) of this section, then the agency shall promptly notify the applicant that the agency will take appropriate action to insure that the objectives and procedures of NEPA are achieved. (c) While work on a required program environmental impact statement is in progress and the action is not covered by an existing program statement, [[Page 887]] agencies shall not undertake in the interim any major Federal action covered by the program which may significantly affect the quality of the human environment unless such action: (1) Is justified independently of the program; (2) Is itself accompanied by an adequate environmental impact statement; and (3) Will not prejudice the ultimate decision on the program. Interim action prejudices the ultimate decision on the program when it tends to determine subsequent development or limit alternatives. (d) This section does not preclude development by applicants of plans or designs or performance of other work necessary to support an application for Federal, State or local permits or assistance. Nothing in this section shall preclude Rural Electrification Administration approval of minimal expenditures not affecting the environment (e.g. long leadtime equipment and purchase options) made by non-governmental entities seeking loan guarantees from the Administration.