                   TITLE 40--PROTECTION OF ENVIRONMENT
 
         CHAPTER I--ENVIRONMENTAL PROTECTION AGENCY (CONTINUED)
 
PART 65_CONSOLIDATED FEDERAL AIR RULE--Table of Contents
 
                        Subpart C_Storage Vessels
 
Sec.  65.48  Reporting provisions.

    (a) Notification of initial startup. If Sec.  65.5(b) requires that 
a notification of initial startup be filed, then the content of the 
notification of initial startup shall at least include the information 
specified in Sec.  65.5(b) and the identification of each storage 
vessel, its capacity, and the types of regulated material stored in the 
storage vessel.
    (b) Periodic reports. Report the information specified in paragraphs 
(b)(1) through (3) of this section, as applicable, in the periodic 
report specified in Sec.  65.5(e).
    (1) Inspection results. Report the following information for each 
inspection conducted in accordance with Sec.  65.43(c) and Sec.  
65.44(c) in which an IFR or EFR failure is detected in the control 
equipment:
    (i) If an IFR type A failure or an EFR failure is observed for 
vessels for which inspections are required under Sec.  65.43(c)(1)(i), 
Sec.  65.43(c)(2)(ii)(A), or Sec.  65.44(c)(10), each report shall 
include the inspection results record listed in Sec.  65.47(c)(1)(ii). 
If an extension is utilized in accordance with Sec.  65.43(d)(1) or 
Sec.  65.44(d)(1), the report shall include the records listed in Sec.  
65.47(c)(1)(ii) plus the documentation specified in Sec.  65.47(d)(1).

[[Page 52]]

    (ii) If an IFR type B failure is observed for vessels for which 
inspections are required under Sec.  65.43(c)(1)(ii), (c)(2)(i), or 
(c)(2)(ii)(B), each report shall include a copy of the records listed in 
Sec.  65.47(c)(1)(ii).
    (2) Seal gap measurement results. (i) For each vessel whose seal 
gaps are measured during the reporting period, identify each seal gap 
measurement made in accordance with Sec.  65.44(c) in which the 
requirements of Sec.  65.44(c)(7) or (8) are met.
    (ii) For each seal gap measurement made in accordance with Sec.  
65.44(c) in which the requirements of Sec.  65.44(c)(7) or (8) are not 
met, from the records kept pursuant to Sec.  65.47(c)(2), report the 
date of the measurements, results of the calculations, and note which 
seal gap measurements did not conform to the specifications in Sec.  
65.44(c)(7) and (8).
    (3) Extension documentation. If an extension is utilized in 
accordance with Sec.  65.44(c)(9), the owner or operator shall include 
the documentation specified in Sec.  65.47(d)(2) in the next report 
required by Sec.  65.5(e).
    (c) Special notifications. An owner or operator who elects to comply 
with Sec.  65.43, Sec.  65.44, or Sec.  65.45 shall submit, as 
applicable, the reports specified in paragraphs (c)(1) and (2) of this 
section except as specified in paragraph (c)(3) of this section. Each 
written notification or report shall also include the information 
specified in Sec.  65.5(f).
    (1) Refilling notification. In order to afford the Administrator the 
opportunity to have an observer present, notify the Administrator prior 
to refilling of a storage vessel that has been emptied. If the storage 
vessel is equipped with an internal floating roof as specified in Sec.  
65.43, an external floating roof as specified in Sec.  65.44, or an 
external floating roof converted to an internal floating roof as 
specified in Sec.  65.45, the notification shall meet either of the 
following requirements, as applicable.
    (i) Notify the Administrator in writing at least 30 calendar days 
prior to the refilling of each storage vessel; or
    (ii) If the inspection is not planned and the owner or operator 
could not have known about the inspection 30 calendar days in advance of 
refilling the vessel, the owner or operator shall notify the 
Administrator as soon as practical, but no later than 7 calendar days 
prior to the refilling of the storage vessel. Notification may be made 
by telephone and immediately followed by written documentation 
demonstrating why the inspection was unplanned. Alternatively, the 
notification including the written documentation may be made in writing 
and sent so that it is received by the Administrator at least 7 calendar 
days prior to refilling.
    (2) Seal gap measurement notification. In order to afford the 
Administrator the opportunity to have an observer present during seal 
gap measurements, the owner or operator of a storage vessel equipped 
with an external floating roof as specified in Sec.  65.44 shall meet 
either of the following notification requirements, as applicable:
    (i) Notify the Administrator in writing at least 30 calendar days in 
advance of any seal gap measurements; or
    (ii) If the seal gap measurements are not planned and the owner or 
operator could not have known about the seal gap measurements 30 
calendar days in advance, the owner or operator shall notify the 
Administrator as soon as practical, but no later than 7 calendar days 
prior to the seal gap measurements. Notification may be made by 
telephone and immediately followed by written documentation 
demonstrating why the seal gap measurements were unplanned. 
Alternatively, the notification including the written documentation may 
be made in writing and sent so that it is received by the Administrator 
at least 7 calendar days prior to refilling.
    (3) Notification waiver. Where a notification required by paragraphs 
(c)(1) or (2) of this section is sent to a delegated State or local 
agency, a copy of the notification to the Administrator is not required. 
A delegated State or local agency may waive the requirements for these 
notifications.
    (d) Compliance certification. For sources subject to the compliance 
certification provisions of title V, a recertification of continuous 
compliance with Sec.  65.43(b)(1) and Sec.  65.44(b)(1) shall be based 
on the annual inspections required by Sec.  65.43(c)(1)(i) and 
(c)(2)(ii)(A)

[[Page 53]]

and any observations made at other times when the roof is viewed.