Sec.  68.175  Prevention program/Program 3.

    (a) For each Program 3 process, the owner or operator shall provide 
the information indicated in paragraphs (b) through (p) of this section. 
If the same information applies to more than one covered process, the 
owner or operator may provide the information only once, but shall 
indicate to which processes the information applies.
    (b) The five- or six-digit NAICS code that most closely corresponds 
to the process.
    (c) The name(s) of the substance(s) covered.
    (d) The date on which the safety information was last reviewed or 
revised.
    (e) The date of completion of the most recent PHA or update and the 
technique used.
    (1) The expected date of completion of any changes resulting from 
the PHA;
    (2) Major hazards identified;
    (3) Process controls in use;
    (4) Mitigation systems in use;
    (5) Monitoring and detection systems in use; and
    (6) Changes since the last PHA.
    (f) The date of the most recent review or revision of operating 
procedures.
    (g) The date of the most recent review or revision of training 
programs;
    (1) The type of training provided--classroom, classroom plus on the 
job, on the job; and
    (2) The type of competency testing used.
    (h) The date of the most recent review or revision of maintenance 
procedures and the date of the most recent equipment inspection or test 
and the equipment inspected or tested.
    (i) The date of the most recent change that triggered management of 
change procedures and the date of the most recent review or revision of 
management of change procedures.
    (j) The date of the most recent pre-startup review.
    (k) The date of the most recent compliance audit and the expected 
date of completion of any changes resulting from the compliance audit;
    (l) The date of the most recent incident investigation and the 
expected date of completion of any changes resulting from the 
investigation;

[[Page 188]]

    (m) The date of the most recent review or revision of employee 
participation plans;
    (n) The date of the most recent review or revision of hot work 
permit procedures;
    (o) The date of the most recent review or revision of contractor 
safety procedures; and
    (p) The date of the most recent evaluation of contractor safety 
performance.