              TITLE 44--EMERGENCY MANAGEMENT AND ASSISTANCE
 
 CHAPTER I--FEDERAL EMERGENCY MANAGEMENT AGENCY, DEPARTMENT OF HOMELAND 
                                SECURITY
 
PART 60_CRITERIA FOR LAND MANAGEMENT AND USE--Table of Contents
 
      Subpart A_Requirements for Flood Plain Management Regulations
 
Sec.  60.3  Flood plain management criteria for flood-prone areas.

    The Administrator will provide the data upon which flood plain 
management regulations shall be based. If the Administrator has not 
provided sufficient data to furnish a basis for these regulations in a 
particular community, the community shall obtain, review and reasonably 
utilize data available from other Federal, State or other sources 
pending receipt of data from the Administrator. However, when special 
flood hazard area designations and water surface elevations have been 
furnished by the Administrator, they shall apply. The symbols defining 
such special flood hazard designations are set forth in Sec.  64.3 of 
this subchapter. In all cases the minimum requirements governing the 
adequacy of the flood plain management regulations for flood-prone areas 
adopted by a particular community depend on the amount of technical data 
formally provided to the community by the Administrator. Minimum 
standards for communities are as follows:
    (a) When the Administrator has not defined the special flood hazard 
areas within a community, has not provided water surface elevation data, 
and has not provided sufficient data to identify the floodway or coastal 
high hazard area, but the community has indicated the presence of such 
hazards by submitting an application to participate in the Program, the 
community shall:
    (1) Require permits for all proposed construction or other 
development in

[[Page 237]]

the community, including the placement of manufactured homes, so that it 
may determine whether such construction or other development is proposed 
within flood-prone areas;
    (2) Review proposed development to assure that all necessary permits 
have been received from those governmental agencies from which approval 
is required by Federal or State law, including section 404 of the 
Federal Water Pollution Control Act Amendments of 1972, 33 U.S.C. 1334;
    (3) Review all permit applications to determine whether proposed 
building sites will be reasonably safe from flooding. If a proposed 
building site is in a flood-prone area, all new construction and 
substantial improvements shall (i) be designed (or modified) and 
adequately anchored to prevent flotation, collapse, or lateral movement 
of the structure resulting from hydrodynamic and hydrostatic loads, 
including the effects of buoyancy, (ii) be constructed with materials 
resistant to flood damage, (iii) be constructed by methods and practices 
that minimize flood damages, and (iv) be constructed with electrical, 
heating, ventilation, plumbing, and air conditioning equipment and other 
service facilities that are designed and/or located so as to prevent 
water from entering or accumulating within the components during 
conditions of flooding.
    (4) Review subdivision proposals and other proposed new development, 
including manufactured home parks or subdivisions, to determine whether 
such proposals will be reasonably safe from flooding. If a subdivision 
proposal or other proposed new development is in a flood-prone area, any 
such proposals shall be reviewed to assure that (i) all such proposals 
are consistent with the need to minimize flood damage within the flood-
prone area, (ii) all public utilities and facilities, such as sewer, 
gas, electrical, and water systems are located and constructed to 
minimize or eliminate flood damage, and (iii) adequate drainage is 
provided to reduce exposure to flood hazards;
    (5) Require within flood-prone areas new and replacement water 
supply systems to be designed to minimize or eliminate infiltration of 
flood waters into the systems; and
    (6) Require within flood-prone areas (i) new and replacement 
sanitary sewage systems to be designed to minimize or eliminate 
infiltration of flood waters into the systems and discharges from the 
systems into flood waters and (ii) onsite waste disposal systems to be 
located to avoid impairment to them or contamination from them during 
flooding.
    (b) When the Administrator has designated areas of special flood 
hazards (A zones) by the publication of a community's FHBM or FIRM, but 
has neither produced water surface elevation data nor identified a 
floodway or coastal high hazard area, the community shall:
    (1) Require permits for all proposed construction and other 
developments including the placement of manufactured homes, within Zone 
A on the community's FHBM or FIRM;
    (2) Require the application of the standards in paragraphs (a) (2), 
(3), (4), (5) and (6) of this section to development within Zone A on 
the community's FHBM or FIRM;
    (3) Require that all new subdivision proposals and other proposed 
developments (including proposals for manufactured home parks and 
subdivisions) greater than 50 lots or 5 acres, whichever is the lesser, 
include within such proposals base flood elevation data;
    (4) Obtain, review and reasonably utilize any base flood elevation 
and floodway data available from a Federal, State, or other source, 
including data developed pursuant to paragraph (b)(3) of this section, 
as criteria for requiring that new construction, substantial 
improvements, or other development in Zone A on the community's FHBM or 
FIRM meet the standards in paragraphs (c)(2), (c)(3), (c)(5), (c)(6), 
(c)(12), (c)(14), (d)(2) and (d)(3) of this section;
    (5) Where base flood elevation data are utilized, within Zone A on 
the community's FHBM or FIRM:
    (i) Obtain the elevation (in relation to mean sea level) of the 
lowest floor (including basement) of all new and substantially improved 
structures, and
    (ii) Obtain, if the structure has been floodproofed in accordance 
with paragraph (c)(3)(ii) of this section, the elevation (in relation to 
mean sea level)

[[Page 238]]

to which the structure was floodproofed, and
    (iii) Maintain a record of all such information with the official 
designated by the community under Sec.  59.22 (a)(9)(iii);
    (6) Notify, in riverine situations, adjacent communities and the 
State Coordinating Office prior to any alteration or relocation of a 
watercourse, and submit copies of such notifications to the 
Administrator;
    (7) Assure that the flood carrying capacity within the altered or 
relocated portion of any watercourse is maintained;
    (8) Require that all manufactured homes to be placed within Zone A 
on a community's FHBM or FIRM shall be installed using methods and 
practices which minimize flood damage. For the purposes of this 
requirement, manufactured homes must be elevated and anchored to resist 
flotation, collapse, or lateral movement. Methods of anchoring may 
include, but are not to be limited to, use of over-the-top or frame ties 
to ground anchors. This requirement is in addition to applicable State 
and local anchoring requirements for resisting wind forces.
    (c) When the Administrator has provided a notice of final flood 
elevations for one or more special flood hazard areas on the community's 
FIRM and, if appropriate, has designated other special flood hazard 
areas without base flood elevations on the community's FIRM, but has not 
identified a regulatory floodway or coastal high hazard area, the 
community shall:
    (1) Require the standards of paragraph (b) of this section within 
all A1-30 zones, AE zones, A zones, AH zones, and AO zones, on the 
community's FIRM;
    (2) Require that all new construction and substantial improvements 
of residential structures within Zones A1-30, AE and AH zones on the 
community's FIRM have the lowest floor (including basement) elevated to 
or above the base flood level, unless the community is granted an 
exception by the Administrator for the allowance of basements in 
accordance with Sec.  60.6 (b) or (c);
    (3) Require that all new construction and substantial improvements 
of non-residential structures within Zones A1-30, AE and AH zones on the 
community's firm (i) have the lowest floor (including basement) elevated 
to or above the base flood level or, (ii) together with attendant 
utility and sanitary facilities, be designed so that below the base 
flood level the structure is watertight with walls substantially 
impermeable to the passage of water and with structural components 
having the capability of resisting hydrostatic and hydrodynamic loads 
and effects of buoyancy;
    (4) Provide that where a non-residential structure is intended to be 
made watertight below the base flood level, (i) a registered 
professional engineer or architect shall develop and/or review 
structural design, specifications, and plans for the construction, and 
shall certify that the design and methods of construction are in 
accordance with accepted standards of practice for meeting the 
applicable provisions of paragraph (c)(3)(ii) or (c)(8)(ii) of this 
section, and (ii) a record of such certificates which includes the 
specific elevation (in relation to mean sea level) to which such 
structures are floodproofed shall be maintained with the official 
designated by the community under Sec.  59.22(a)(9)(iii);
    (5) Require, for all new construction and substantial improvements, 
that fully enclosed areas below the lowest floor that are usable solely 
for parking of vehicles, building access or storage in an area other 
than a basement and which are subject to flooding shall be designed to 
automatically equalize hydrostatic flood forces on exterior walls by 
allowing for the entry and exit of floodwaters. Designs for meeting this 
requirement must either be certified by a registered professional 
engineer or architect or meet or exceed the following minimum criteria: 
A minimum of two openings having a total net area of not less than one 
square inch for every square foot of enclosed area subject to flooding 
shall be provided. The bottom of all openings shall be no higher than 
one foot above grade. Openings may be equipped with screens, louvers, 
valves, or other coverings or devices provided that they permit the 
automatic entry and exit of floodwaters.

[[Page 239]]

    (6) Require that manufactured homes that are placed or substantially 
improved within Zones A1-30, AH, and AE on the community's FIRM on sites
    (i) Outside of a manufactured home park or subdivision,
    (ii) In a new manufactured home park or subdivision,
    (iii) In an expansion to an existing manufactured home park or 
subdivision, or
    (iv) In an existing manufactured home park or subdivision on which a 
manufactured home has incurred ``substantial damage'' as the result of a 
flood, be elevated on a permanent foundation such that the lowest floor 
of the manufactured home is elevated to or above the base flood 
elevation and be securely anchored to an adequately anchored foundation 
system to resist floatation collapse and lateral movement.
    (7) Require within any AO zone on the community's FIRM that all new 
construction and substantial improvements of residential structures have 
the lowest floor (including basement) elevated above the highest 
adjacent grade at least as high as the depth number specified in feet on 
the community's FIRM (at least two feet if no depth number is 
specified);
    (8) Require within any AO zone on the community's FIRM that all new 
construction and substantial improvements of nonresidential structures 
(i) have the lowest floor (including basement) elevated above the 
highest adjacent grade at least as high as the depth number specified in 
feet on the community's FIRM (at least two feet if no depth number is 
specified), or (ii) together with attendant utility and sanitary 
facilities be completely floodproofed to that level to meet the 
floodproofing standard specified in Sec.  60.3(c)(3)(ii);
    (9) Require within any A99 zones on a community's FIRM the standards 
of paragraphs (a)(1) through (a)(4)(i) and (b)(5) through (b)(9) of this 
section;
    (10) Require until a regulatory floodway is designated, that no new 
construction, substantial improvements, or other development (including 
fill) shall be permitted within Zones A1-30 and AE on the community's 
FIRM, unless it is demonstrated that the cumulative effect of the 
proposed development, when combined with all other existing and 
anticipated development, will not increase the water surface elevation 
of the base flood more than one foot at any point within the community.
    (11) Require within Zones AH and AO, adequate drainage paths around 
structures on slopes, to guide floodwaters around and away from proposed 
structures.
    (12) Require that manufactured homes to be placed or substantially 
improved on sites in an existing manufactured home park or subdivision 
within Zones A-1-30, AH, and AE on the community's FIRM that are not 
subject to the provisions of paragraph (c)(6) of this section be 
elevated so that either
    (i) The lowest floor of the manufactured home is at or above the 
base flood elevation, or
    (ii) The manufactured home chassis is supported by reinforced piers 
or other foundation elements of at least equivalent strength that are no 
less than 36 inches in height above grade and be securely anchored to an 
adequately anchored foundation system to resist floatation, collapse, 
and lateral movement.
    (13) Notwithstanding any other provisions of Sec.  60.3, a community 
may approve certain development in Zones Al-30, AE, and AH, on the 
community's FIRM which increase the water surface elevation of the base 
flood by more than one foot, provided that the community first applies 
for a conditional FIRM revision, fulfills the requirements for such a 
revision as established under the provisions of Sec.  65.12, and 
receives the approval of the Administrator.
    (14) Require that recreational vehicles placed on sites within Zones 
A1-30, AH, and AE on the community's FIRM either
    (i) Be on the site for fewer than 180 consecutive days,
    (ii) Be fully licensed and ready for highway use, or
    (iii) Meet the permit requirements of paragraph (b)(1) of this 
section and the elevation and anchoring requirements for ``manufactured 
homes'' in paragraph (c)(6) of this section.

[[Page 240]]


A recreational vehicle is ready for highway use if it is on its wheels 
or jacking system, is attached to the site only by quick disconnect type 
utilities and security devices, and has no permanently attached 
additions.
    (d) When the Administrator has provided a notice of final base flood 
elevations within Zones A1-30 and/or AE on the community's FIRM and, if 
appropriate, has designated AO zones, AH zones, A99 zones, and A zones 
on the community's FIRM, and has provided data from which the community 
shall designate its regulatory floodway, the community shall:
    (1) Meet the requirements of paragraphs (c) (1) through (14) of this 
section;
    (2) Select and adopt a regulatory floodway based on the principle 
that the area chosen for the regulatory floodway must be designed to 
carry the waters of the base flood, without increasing the water surface 
elevation of that flood more than one foot at any point;
    (3) Prohibit encroachments, including fill, new construction, 
substantial improvements, and other development within the adopted 
regulatory floodway unless it has been demonstrated through hydrologic 
and hydraulic analyses performed in accordance with standard engineering 
practice that the proposed encroachment would not result in any increase 
in flood levels within the community during the occurrence of the base 
flood discharge;
    (4) Notwithstanding any other provisions of Sec.  60.3, a community 
may permit encroachments within the adopted regulatory floodway that 
would result in an increase in base flood elevations, provided that the 
community first applies for a conditional FIRM and floodway revision, 
fulfills the requirements for such revisions as established under the 
provisions of Sec.  65.12, and receives the approval of the 
Administrator.
    (e) When the Administrator has provided a notice of final base flood 
elevations within Zones A1-30 and/or AE on the community's FIRM and, if 
appropriate, has designated AH zones, AO zones, A99 zones, and A zones 
on the community's FIRM, and has identified on the community's FIRM 
coastal high hazard areas by designating Zones V1-30, VE, and/or V, the 
community shall:
    (1) Meet the requirements of paragraphs (c)(1) through (14) of this 
section;
    (2) Within Zones V1-30, VE, and V on a community's FIRM, (i ) obtain 
the elevation (in relation to mean sea level) of the bottom of the 
lowest structural member of the lowest floor (excluding pilings and 
columns) of all new and substantially improved structures, and whether 
or not such structures contain a basement, and (ii) maintain a record of 
all such information with the official designated by the community under 
Sec.  59.22(a)(9)(iii);
    (3) Provide that all new construction within Zones V1-30, VE, and V 
on the community's FIRM is located landward of the reach of mean high 
tide;
    (4) Provide that all new construction and substantial improvements 
in Zones V1-30 and VE, and also Zone V if base flood elevation data is 
available, on the community's FIRM, are elevated on pilings and columns 
so that (i) the bottom of the lowest horizontal structural member of the 
lowest floor (excluding the pilings or columns) is elevated to or above 
the base flood level; and (ii) the pile or column foundation and 
structure attached thereto is anchored to resist flotation, collapse and 
lateral movement due to the effects of wind and water loads acting 
simultaneously on all building components. Water loading values used 
shall be those associated with the base flood. Wind loading values used 
shall be those required by applicable State or local building standards. 
A registered professional engineer or architect shall develop or review 
the structural design, specifications and plans for the construction, 
and shall certify that the design and methods of construction to be used 
are in accordance with accepted standards of practice for meeting the 
provisions of paragraphs (e)(4) (i) and (ii) of this section.
    (5) Provide that all new construction and substantial improvements 
within Zones V1-30, VE, and V on the community's FIRM have the space 
below the lowest floor either free of obstruction or constructed with 
non-supporting breakaway walls, open wood lattice-

[[Page 241]]

work, or insect screening intended to collapse under wind and water 
loads without causing collapse, displacement, or other structural damage 
to the elevated portion of the building or supporting foundation system. 
For the purposes of this section, a breakway wall shall have a design 
safe loading resistance of not less than 10 and no more than 20 pounds 
per square foot. Use of breakway walls which exceed a design safe 
loading resistance of 20 pounds per square foot (either by design or 
when so required by local or State codes) may be permitted only if a 
registered professional engineer or architect certifies that the designs 
proposed meet the following conditions:
    (i) Breakaway wall collapse shall result from a water load less than 
that which would occur during the base flood; and,
    (ii) The elevated portion of the building and supporting foundation 
system shall not be subject to collapse, displacement, or other 
structural damage due to the effects of wind and water loads acting 
simultaneously on all building components (structural and non-
structural). Water loading values used shall be those associated with 
the base flood. Wind loading values used shall be those required by 
applicable State or local building standards.

Such enclosed space shall be useable solely for parking of vehicles, 
building access, or storage.
    (6) Prohibit the use of fill for structural support of buildings 
within Zones V1-30, VE, and V on the community's FIRM;
    (7) Prohibit man-made alteration of sand dunes and mangrove stands 
within Zones V1-30, VE, and V on the community's FIRM which would 
increase potential flood damage.
    (8) Require that manufactured homes placed or substantially improved 
within Zones V1-30, V, and VE on the community's FIRM on sites
    (i) Outside of a manufactured home park or subdivision,
    (ii) In a new manufactured home park or subdivision,
    (iii) In an expansion to an existing manufactured home park or 
subdivision, or
    (iv) In an existing manufactured home park or subdivision on which a 
manufactured home has incurred ``substantial damage'' as the result of a 
flood, meet the standards of paragraphs (e)(2) through (7) of this 
section and that manufactured homes placed or substantially improved on 
other sites in an existing manufactured home park or subdivision within 
Zones VI-30, V, and VE on the community's FIRM meet the requirements of 
paragraph (c)(12) of this section.
    (9) Require that recreational vehicles placed on sites within Zones 
V1-30, V, and VE on the community's FIRM either
    (i) Be on the site for fewer than 180 consecutive days,
    (ii) Be fully licensed and ready for highway use, or
    (iii) Meet the requirements in paragraphs (b)(1) and (e) (2) through 
(7) of this section.

A recreational vehicle is ready for highway use if it is on its wheels 
or jacking system, is attached to the site only by quick disconnect type 
utilities and security devices, and has no permanently attached 
additions.
    (f) When the Administrator has provided a notice of final base flood 
elevations within Zones A1-30 or AE on the community's FIRM, and, if 
appropriate, has designated AH zones, AO zones, A99 zones, and A zones 
on the community's FIRM, and has identified flood protection restoration 
areas by designating Zones AR, AR/A1-30, AR/AE, AR/AH, AR/AO, or AR/A, 
the community shall:
    (1) Meet the requirements of paragraphs (c)(1) through (14) and 
(d)(1) through (4) of this section.
    (2) Adopt the official map or legal description of those areas 
within Zones AR, AR/A1-30, AR/AE, AR/AH, AR/A, or AR/AO that are 
designated developed areas as defined in Sec.  59.1 in accordance with 
the eligibility procedures under Sec.  65.14.
    (3) For all new construction of structures in areas within Zone AR 
that are designated as developed areas and in other areas within Zone AR 
where the AR flood depth is 5 feet or less:
    (i) Determine the lower of either the AR base flood elevation or the 
elevation that is 3 feet above highest adjacent grade; and

[[Page 242]]

    (ii) Using this elevation, require the standards of paragraphs 
(c)(1) through (14) of this section.
    (4) For all new construction of structures in those areas within 
Zone AR that are not designated as developed areas where the AR flood 
depth is greater than 5 feet:
    (i) Determine the AR base flood elevation; and
    (ii) Using that elevation require the standards of paragraphs (c)(1) 
through (14) of this section.
    (5) For all new construction of structures in areas within Zone AR/
A1-30, AR/AE, AR/AH, AR/AO, and AR/A:
    (i) Determine the applicable elevation for Zone AR from paragraphs 
(a)(3) and (4) of this section;
    (ii) Determine the base flood elevation or flood depth for the 
underlying A1-30, AE, AH, AO and A Zone; and
    (iii) Using the higher elevation from paragraphs (a)(5)(i) and (ii) 
of this section require the standards of paragraphs (c)(1) through (14) 
of this section.
    (6) For all substantial improvements to existing construction within 
Zones AR/A1-30, AR/AE, AR/AH, AR/AO, and AR/A:
    (i) Determine the A1-30 or AE, AH, AO, or A Zone base flood 
elevation; and
    (ii) Using this elevation apply the requirements of paragraphs 
(c)(1) through (14) of this section.
    (7) Notify the permit applicant that the area has been designated as 
an AR, AR/A1-30, AR/AE, AR/AH, AR/AO, or AR/A Zone and whether the 
structure will be elevated or protected to or above the AR base flood 
elevation.

[41 FR 46975, Oct. 26, 1976]

    Editorial Note: For Federal Register citations affecting Sec.  60.3, 
see the List of CFR Sections Affected, which appears in the Finding Aids 
section of the printed volume and on GPO Access.