[Code of Federal Regulations]
[Title 44, Volume 1]
[Revised as of October 1, 2007]
From the U.S. Government Printing Office via GPO Access
[CITE: 44CFR72.7]

[Page 357-358]
 
              TITLE 44--EMERGENCY MANAGEMENT AND ASSISTANCE
 
 CHAPTER I--FEDERAL EMERGENCY MANAGEMENT AGENCY, DEPARTMENT OF HOMELAND 
                                SECURITY
 
PART 72_PROCEDURES AND FEES FOR PROCESSING MAP CHANGES--Table of Contents
 
Sec.  72.7  Resubmittals.

    (a) Resubmittals of CLOMA, CLOMR, CLOMR-F, LOMR, LOMR-F, or PMR 
requests more than 90 days after FEMA notification that the requests 
were denied or after FEMA ended its review because the requester 
provided insufficient information will be treated as original 
submissions and subject to all submittal/payment procedures described in 
Sec.  72.4. The procedure in Sec.  72.4 also applies to a resubmitted 
request (regardless of when submitted) if the project on which the 
request is based has been altered significantly in design or scope other 
than as necessary to respond to comments, concerns, or other findings 
made by FEMA regarding the original submission.
    (b) When LOMR, LOMR-F, or PMR requests are made after FEMA issues 
CLOMRs or CLOMR-Fs, the procedures in Sec.  72.4 and the appropriate fee 
apply, as referenced in Sec.  72.3(c). When the as-built conditions 
differ from the proposed conditions on which FEMA issued the CLOMRs or 
CLOMR-Fs, the

[[Page 358]]

reduced fee for as-built requests will not apply.

[62 FR 5738, Feb. 6, 1997]