Sec.  78.6  Flood Mitigation Plan approval process.

    The State POC will forward all Flood Mitigation Plans to the FEMA 
Regional Director for approval. The Regional Director will notify the 
State POC of the approval or disapproval of the plan within 120 days 
after submission. If the Regional Director does not approve a mitigation 
plan, the Regional Director will notify the State POC of the reasons for 
non-approval and offer suggestions for improvement.