[Code of Federal Regulations]
[Title 48, Volume 6]
[Revised as of October 1, 2007]
From the U.S. Government Printing Office via GPO Access
[CITE: 48CFR2009.405]

[Page 362]
 
            TITLE 48--FEDERAL ACQUISITION REGULATIONS SYSTEM
 
                CHAPTER 20--NUCLEAR REGULATORY COMMISSION
 
Sec. 2009.405  Effect of listing.

    Compelling reasons are considered to be present where failure to 
contract with the debarred or suspended contractor would seriously harm 
the agency's programs and prevent accomplishment of mission 
requirements. The Senior Procurement Executive is authorized to make the 
determinations under FAR 9.405. Requests for these determinations must 
be submitted from the Head of the Contracting Activity, through the 
Director, Office of Administration, to the Senior Procurement Executive.