[Code of Federal Regulations]
[Title 48, Volume 6]
[Revised as of October 1, 2007]
From the U.S. Government Printing Office via GPO Access
[CITE: 48CFR2052.211-71]

[Page 389-390]
 
            TITLE 48--FEDERAL ACQUISITION REGULATIONS SYSTEM
 
                CHAPTER 20--NUCLEAR REGULATORY COMMISSION
 
Sec. 2052.211-71  Technical progress report.

    As prescribed at 2011.104-70(b), the contracting officer shall 
insert the following clause in all solicitations and contracts except 
firm fixed price or indefinite delivery contracts to be awarded on a 
time-and-materials or labor-hour basis, or which provide for

[[Page 390]]

issuance of delivery orders for specific products/serviced line items. 
The contracting officer may alter this clause prior to issuance of the 
solicitation or during competition by solicitation amendment. 
Insignificant changes may also be made by the contracting officer on a 
case-by-case basis during negotiation without amending the solicitation.

                  Technical Progress Report (JAN 1993)

    The contractor shall provide a monthly Technical Progress Report to 
the project officer and the contracting officer. The report is due 
within 15 calendar days after the end of the report period and must 
identify the title of the project, the contract number, appropriate 
financial tracking code specified by the NRC Project Officer, project 
manager and/or principal investigator, the contract period of 
performance, and the period covered by the report. Each report must 
include the following for each discrete task/task order:
    (a) A listing of the efforts completed during the period, and 
milestones reached or, if missed, an explanation provided;
    (b) Any problems or delays encountered or anticipated and 
recommendations for resolution. If the recommended resolution involves a 
contract modification, e.g., change in work requirements, level of 
effort (cost) or schedule delay, the contractor shall submit a separate 
letter to the contracting officer identifying the required change and 
estimated cost impact;
    (c) A summary of progress to date; and
    (d) Plans for the next reporting period.

                             (End of clause)