Sec. 2052.214-72  Bid evaluation.

    As prescribed at 2014.201-670(c), the contracting officer shall 
insert the following provision in applicable invitations for bids 
(paragraph ``(f)'' of this provision is optional):

                        Bid Evaluation (JAN 1993)

    (a) Award will be made to that responsive, responsible bidder within 
the meaning of FAR Subpart 9.1 whose total bid amount, as set forth by 
the bidder in Section B of this Invitation for Bid (IFB), constitutes 
the lowest overall evaluated final contract price to the Government 
based upon the requirements for the schedule. Bids will be evaluated for 
purposes of award by first ascertaining the sum of the total amount for 
each of the items specified in Section B of this solicitation. This will 
constitute the bidder's ``Total Bid Amount.''
    (b) Bidders shall insert a definite price or indicate ``no charge'' 
in the blank space provided for each item and/or sub-item listed in 
Section B. Unless expressly provided for in the bid, no additional 
charge will be allowed for work performed under the contract other than 
the unit prices stipulated for each item and/or sub-item.
    (c) Any bid which is materially unbalanced as to price for the 
separate items specified in Section B of this IFB may be rejected as 
nonresponsive. An unbalanced bid is defined as one which is based on 
prices which, in the opinion of the NRC, are significantly less than 
cost for some work and/or prices that may be significantly overstated 
for other work.

[[Page 393]]

    (d) Separation charges, in any form, are not solicited. Bids 
containing charges for discontinuance, termination, failure to exercise 
an option, or for any other purpose will cause the bid to be rejected as 
nonresponsive.
    (e) A preaward on-site survey of the bidder's facilities, equipment, 
etc., in accordance with FAR 9.105 and 9.106, may be made by 
representatives of the Commission for the purpose of determining whether 
the bidder is responsible within the meaning of FAR 9.1, and whether the 
bidder possesses qualifications that are conducive to the production of 
work that will meet the requirements, specifications, and provisions of 
this contract. If requested by the Commission, the prospective 
contractor may also be required to submit statements within * hours 
after receiving the request:
    (1) Concerning their ability to meet any of the minimum standards 
set forth in FAR 9.104,
    (2) Samples of work, and
    (3) Names and addresses of additional clients, Government agencies, 
and/or commercial firms which the bidder is now doing or had done 
business with.
    (f) Notwithstanding paragraph (b) of this section, the award of any 
contract resulting from this solicitation will be made on an ``all or 
none'' basis. Thus, bids submitted on fewer than the items listed in 
Section B of this IFB, or on fewer than the estimated quantity, will 
cause the bid to be rejected as nonresponsive.
    *To be inserted into solicitation.