Sec. 2052.231-70  Precontract costs.

    As prescribed in 2031.109-70, following clause may be used in all 
cost type contracts when costs in connection with work under the 
contract will be incurred by the contractor before the effective date of 
the contract. Approval for use of this clause must be obtained at one 
level above the contracting officer.

                      Precontract Costs (JAN 1993)

    Allowable costs under this contract include costs incurred by the 
contractor in connection with the work covered by this contract during 
the period from * and including * to the effective date of this contract 
that would have been allowable under the terms of this contract if this 
contract had been in effect during that period. However, the costs may 
not in aggregate exceed * which is included in the estimated cost of 
this contract.
    *To be incorporated into any resultant contract.

                             (End of clause)