[Code of Federal Regulations]
[Title 48, Volume 5]
[Revised as of October 1, 2007]
From the U.S. Government Printing Office via GPO Access
[CITE: 48CFR752.7009]

[Page 80]
 
            TITLE 48--FEDERAL ACQUISITION REGULATIONS SYSTEM
 
             CHAPTER 7--AGENCY FOR INTERNATIONAL DEVELOPMENT
 
Sec. 752.7009  Marking.

    The following clause is for use in all USAID contracts performed in 
whole or in part overseas.

                           Marking (JAN 1993)

    (a) It is USAID policy that USAID-financed commodities and shipping 
containers, and project construction sites and other project locations 
be suitably marked with the USAID emblem. Shipping containers are also 
to be marked with the last five digits of the USAID financing document 
number. As a general rule, marking is not required for raw materials 
shipped in bulk (such as coal, grain, etc.), or for semifinished 
products which are not packaged.
    (b) Specific guidance on marking requirements should be obtained 
prior to procurement of commodities to be shipped, and as early as 
possible for project construction sites and other project locations. 
This guidance will be provided through the cognizant technical office 
indicated on the cover page of this contract, or by the Mission Director 
in the Cooperating Country to which commodities are being shipped, or in 
which the project site is located.
    (c) Authority to waive marking requirements is vested with the 
Regional Assistant Administrators, and with Mission Directors.
    (d) A copy of any specific marking instructions or waivers from 
marking requirements is to be sent to the Contracting Officer; the 
original should be retained by the Contractor.

[49 FR 13259, Apr. 3, 1984, as amended at 58 FR 8703, Feb. 17, 1993]