[Code of Federal Regulations]
[Title 48, Volume 5]
[Revised as of October 1, 2007]
From the U.S. Government Printing Office via GPO Access
[CITE: 48CFR852.236-88]

[Page 252-253]
 
            TITLE 48--FEDERAL ACQUISITION REGULATIONS SYSTEM
 
                CHAPTER 8--DEPARTMENT OF VETERANS AFFAIRS
 
Sec. 852.236-88  Contract changes--supplement.

    As prescribed in 836.578, insert the following clause:

                 Contract Changes--Supplement (JUL 2002)

    The clauses entitled ``Changes'' in FAR 52.243-4 and ``Differing 
Site Conditions'' in FAR 52.236-2 are supplemented as follows:
    (a) Paragraphs (a)(1) through (a)(4) apply to proposed contract 
changes costing over $500,000:
    (1) When requested by the contracting officer, the contractor shall 
submit proposals for changes in work to the resident engineer. 
Proposals, to be submitted as expeditiously as possible but within 30 
calendar days after receipt of request, shall be in legible form, 
original and two copies, with an itemized breakdown that will include 
material, quantities, unit prices, labor costs (separated into trades), 
construction equipment, etc. (Labor costs are to be identified with 
specific material placed or operation performed.) The contractor must 
obtain and furnish with a proposal an itemized breakdown as described 
above, signed by each subcontractor participating in the change 
regardless of tier. When certified cost or pricing data are required 
under FAR Subpart 15.403, the cost or pricing data shall be submitted in 
accordance with FAR 15.403-5.
    (2) When the necessity to proceed with a change does not allow 
sufficient time to negotiate a modification or because of failure to 
reach an agreement, the contracting officer may issue a change order 
instructing the contractor to proceed on the basis of a tentative price 
based on the best estimate available at the time, with the firm price to 
be determined later. Furthermore, when the change order is issued, the 
contractor shall submit a proposal, which includes the information 
required by paragraph (a)(1), for cost of changes in work within 30 
calendar days.
    (3) The contracting officer will consider issuing a settlement by 
determination to the contract if the contractor's proposal required by 
paragraphs (a) and (b) of this clause is not received within 30 calendar 
days or if agreement has not been reached.
    (4) Bond premium adjustment, consequent upon changes ordered, will 
be made as elsewhere specified at the time of final settlement under the 
contract and will not be included in the individual change.
    (b) Paragraphs (b)(1) through (b)(11) apply to proposed contract 
changes costing $500,000 or less:
    (1) When requested by the contracting officer, the contractor shall 
submit proposals for changes in work to the resident engineer. 
Proposals, to be submitted as expeditiously as possible but within 30 
calendar days after receipt of request, shall be in legible form, 
original and two copies, with an itemized breakdown that will include 
material, quantities, unit prices, labor costs (separated into trades), 
construction equipment, etc. (Labor costs are to be identified with 
specific material placed or operation performed.) The contractor must 
obtain and furnish with a proposal an intemized breakdown as described 
above, signed by each subcontractor participating in the change 
regardless of tier. When certified cost or pricing data or information 
other than cost or pricing data are required under FAR 15.403, the data 
shall be submitted in accordance with FAR 15.403-5. No itemized 
breakdown will be required for proposals amounting to less than $1,000.
    (2) When the necessity to proceed with a change does not allow 
sufficient time to negotiate a modification or because of failure to 
reach an agreement, the contracting officer may issue a change order 
instructing the contractor to proceed on the basis of a tentative price 
based on the best estimate available at the time, with the firm price to 
be determined later. Furthermore, when the change order is issued, the 
contractor shall submit with 30 calendar days a proposal, which includes 
the information required by paragraph (b)(1), for the cost of the 
changes in work.
    (3) The contracting officer will consider issuing a settlement by 
determination to the contract if the contractor's proposal required by 
paragraphs (a) and (b) of this clause is not received within 30 calendar 
days or if agreement has not been reached.
    (4) Allowances not to exceed 10 percent each for overhead and profit 
for the party performing the work will be based on the value of labor, 
material, and use of construction equipment required to accomplish the 
change. As the value of the change increases, a declining scale will be 
used in negotiating the percentage of overhead and profit. Allowable 
percentages on changes will not exceed

[[Page 253]]

the following: 10 percent overhead and 10 percent profit on the first 
$20,000; 7\1/2\ percent overhead and 7\1/2\ percent profit on the next 
$30,000; 5 percent overhead and 5 percent profit on balance over 
$50,000. Profit shall be computed by multiplying the profit percentage 
by the sum of the direct costs and computed overhead costs.
    (5) The prime contractor's or upper-tier subcontractor's fee on work 
performed by lower-tier subcontractors will be based on the net 
increased cost to the prime contractor or upper-tier subcontractor, as 
applicable. Allowable fee on changes will not exceed the following: 10 
percent fee on the first $20,000; 7\1/2\ percent fee on the next 
$30,000; and 5 percent fee on balance over $50,000.
    (6) Not more than four percentages, none of which exceed the 
percentages shown above, will be allowed regardless of the number of 
tiers of subcontractors.
    (7) Where the contractor's or subcontractors' portion of a change 
involves credit items, such items must be deducted prior to adding 
overhead and profit for the party performing the work. The contractor's 
fee is limited to the net increase to contractor of subcontractors' 
portions cost computed in accordance herewith.
    (8) Where a change involves credit items only, a proper measure of 
the amount of downward adjustment in the contract price is the 
reasonable cost to the contractor if he/she had performed the deleted 
work. A reasonable allowance for overhead and profit are properly 
includable as part of the downward adjustment for a deductive change. 
The amount of such allowance is subject to negotiation.
    (9) Cost of Federal Old Age Benefit (Social Security) tax and of 
Worker's Compensation and Public Liability insurance appertaining to 
changes are allowable. While no percentage will be allowed thereon for 
overhead or profit, prime contractor's fee will be allowed on such items 
in subcontractor's proposals.
    (10) Overhead and contractor's fee percentages shall be considered 
to include insurance other than mentioned herein, field and office 
supervisors and assistants, security police, use of small tools, 
incidental job burdens, and general home office expenses and no separate 
allowance will be made therefor. Assistants to office supervisors 
include all clerical, stenographic and general office help. Incidental 
job burdens include, but are not necessarily limited to, office 
equipment and supplies, temporary toilets, telephone and conformance to 
OSHA requirements. Items such as, but not necessarily limited to, review 
and coordination, estimating and expediting relative to contract changes 
are associated with field and office supervision and are considered to 
be included in the contractor's overhead and/or fee percentage.
    (11) Bond premium adjustment, consequent upon changes ordered, will 
be made as elsewhere specified at the time of final settlement under the 
contract and will not be included in the individual change.

                             (End of clause)

[49 FR 12629, Mar. 29, 1984, as amended at 50 FR 794, 797, Jan. 7, 1985; 
51 FR 23073, June 25, 1986; 52 FR 28559, 28561, July 31, 1987; 52 FR 
32013, Aug. 25, 1987; 52 FR 49017, Dec. 29, 1987; 53 FR 1632, Jan. 21, 
1988; 61 FR 11587, Mar. 21, 1996; 63 FR 69223, Dec. 16, 1998; 67 FR 
49262, July 30, 2002]