[Code of Federal Regulations]
[Title 49, Volume 4]
[Revised as of October 1, 2007]
From the U.S. Government Printing Office via GPO Access
[CITE: 49CFR230.20]

[Page 472-473]
 
                        TITLE 49--TRANSPORTATION
 
       CHAPTER II--FEDERAL RAILROAD ADMINISTRATION, DEPARTMENT OF 
                             TRANSPORTATION
 
PART 230_STEAM LOCOMOTIVE INSPECTION AND MAINTENANCE STANDARDS--Table of 
 
                            Subpart A_General
 
Sec.  230.20  Alteration and repair report for steam locomotive boilers.

    (a) Alterations. When an alteration is made to a steam locomotive 
boiler, the steam locomotive owner and/or operator shall file an 
alteration report (FRA Form No. 19), detailing the changes to the 
locomotive with the FRA Regional Administrator within 30

[[Page 473]]

days from the date the work was completed. This form shall be attached 
to, and maintained with, the FRA Form No. 4 until such time as a new FRA 
Form No. 4 reflecting the alteration is submitted to the Regional 
Administrator. Alteration reports shall be filed and maintained for the 
life of the boiler. (See appendix B of this part.)
    (b) Welded and riveted repairs to unstayed portions of the boiler. 
Whenever welded or riveted repairs are performed on unstayed portions of 
a steam locomotive boiler, the steam locomotive owner and/or operator 
shall file with the FRA Regional Administrator, within 30 days from the 
time the work was completed, a repair report, FRA Form No. 19, that 
details the work done to the steam locomotive. Repair reports shall be 
filed and maintained for the life of the boiler. (See appendix B of this 
part.)
    (c) Welded and riveted repairs to stayed portions of the boiler. 
Whenever welded or riveted repairs are performed on stayed portions of a 
steam locomotive boiler, the steam locomotive owner and/or operator 
shall complete a repair report (FRA Form No. 19), detailing the work 
done. Repair reports shall be maintained for the life of the boiler. 
(See appendix C of this part.)