[Code of Federal Regulations]
[Title 49, Volume 4]
[Revised as of October 1, 2007]
From the U.S. Government Printing Office via GPO Access
[CITE: 49CFR230.3]

[Page 466-467]
 
                        TITLE 49--TRANSPORTATION
 
       CHAPTER II--FEDERAL RAILROAD ADMINISTRATION, DEPARTMENT OF 
                             TRANSPORTATION
 
PART 230_STEAM LOCOMOTIVE INSPECTION AND MAINTENANCE STANDARDS--Table of 
 
                            Subpart A_General
 
Sec.  230.3  Implementation.

    Except as provided in paragraphs (a) through (c) of this section, 
the locomotive owner and/or operator shall perform a 1472 service day 
inspection that meets the requirements of Sec.  230.17 when the 
locomotive's flues would be required to be removed pursuant to Sec.  
230.10, of the regulations in effect prior to January 18, 2000. (See 49 
CFR parts 200-999, revised October 1, 1978) At the time the locomotive 
owner and/or operator completes this inspection, it must begin to comply 
with the rest of the provisions of this part. Up until such time, and 
except as provided in paragraphs (a) through (c) of this section, 
compliance with the regulations in effect prior to January 18, 2000 (See 
49 CFR parts 200-999, revised October 1, 1978) will constitute full 
compliance with this part. Any interested person may obtain the October 
1, 1978 revision of 49 CFR part s 200-999 by contacting the Federal 
Railroad Administration, Office of Chief Counsel, 400 7th Street, SW, 
Washington, DC 20590.
    (a) One year after January 18, 2000. The following sections of this 
part must be complied with by January 18, 2001: Sec. Sec.  230.7, 
230.51, 230.57, 230.68, 230.70, 230.85, 230.87, 230.115, and 230.116.
    (b) Interim flue removal extensions. FRA will continue to consider 
requests for flue removal extensions under the provisions of Sec.  
230.10 of the regulations in effect prior to January 18, 2000 (See 49 
CFR parts 200-999, revised October 1, 1978) until January 18, 2002.
    (c) Petition for special consideration. The locomotive owner or 
operator may petition FRA for special consideration of this part's 
implementation with respect to any locomotive that has either fully or 
partially satisfied the requirements of Sec.  230.17 within the three 
(3) year period prior to September 25, 1998--provided the locomotive is 
in full compliance with Sec.  230.17 by the time the petition is 
actually filed.\1\
---------------------------------------------------------------------------

    \1\ Note: As an example, where a locomotive has received a proper 
boiler inspection after September 25, 1995 pursuant to Sec. Sec.  230.10 
and 230.11 of the regulations in effect prior to January 18, 2000 but 
has not had its FRA Form No. 4 updated, the locomotive owner or operator 
may update and verify the FRA Form No. 4 for that locomotive, and submit 
a timely petition that requests retroactive credit for the boiler 
inspection. (See 49 CFR parts 200-999, revised October 1, 1978.)
---------------------------------------------------------------------------

    (1) Petition process. Petitions must be filed by January 18, 2001 
and must be accompanied by all relevant documentation to be considered, 
including a FRA Form No. 4 (see appendix C of this part) that has been 
calculated in accordance with Sec.  230.17, and all records that 
demonstrate the number of days the locomotive has been in service. Based 
upon the documentation provided, FRA will calculate the number of 
``service days'' the locomotive has accrued and will notify the 
petitioner

[[Page 467]]

of the number of service days that remain in the locomotive's 1472 
service day cycle. Petitions should be sent to FRA by some form of 
registered mail to ensure a record of delivery. FRA will investigate 
these petitions and will respond to these petitions within one year of 
their receipt. FRA will send its response by some form of registered 
mail to ensure that a record of delivery is created. In its response, 
FRA may grant the petition or deny it. If FRA grants the petition, the 
entirety of the revised requirements will become effective upon receipt 
of FRA's response, unless FRA's response indicates otherwise. If FRA 
denies the petition, the rule will become effective as provided in the 
first paragraph of this section.
    (2) FRA silence. Anyone who does not receive a response within one 
year of the date they filed their petition, whether through 
administrative or postal error, must notify FRA that the response has 
not been received. The notification should be provided to FRA by some 
form of registered mail to ensure a record of delivery. Upon receipt of 
this notification, FRA will ensure that a response is either issued, or 
re-issued, as soon as possible. In the interim, however, any operator 
who is at the end of their inspection cycle under the rules in effect 
prior to January 18, 2000 (See 49 CFR parts 200-999, revised October 1, 
1978) will be allowed to remain in service without conducting the 
required inspection under Sec.  230.17 for an additional six months, or 
until they receive FRA's decision, whichever occurs first.