[Code of Federal Regulations]
[Title 50, Volume 7]
[Revised as of January 1, 2007]
From the U.S. Government Printing Office via GPO Access
[CITE: 50CFR221.3]

[Page 94]
 
                    TITLE 50--WILDLIFE AND FISHERIES
 
  CHAPTER II--NATIONAL MARINE FISHERIES SERVICE, NATIONAL OCEANIC AND 
           ATMOSPHERIC ADMINISTRATION, DEPARTMENT OF COMMERCE
 
PART 221_PRESCRIPTIONS IN FERC HYDROPOWER LICENSES--Table of Contents
 
                      Subpart A_General Provisions
 
Sec. 221.3  How are time periods computed?

    (a) General. Time periods are computed as follows:
    (1) The day of the act or event from which the period begins to run 
is not included.
    (2) The last day of the period is included.
    (i) If that day is a Saturday, Sunday, or federal holiday, the 
period is extended to the next business day.
    (ii) The last day of the period ends at 5 p.m. at the place where 
the filing or other action is due.
    (3) If the period is less than 7 days, any Saturday, Sunday, or 
federal holiday that falls within the period is not included.
    (b) Extensions of time. (1) No extension of time can be granted to 
file a request for a hearing under Sec. 221.21, a notice of 
intervention and response under Sec. 221.22, an answer under Sec. 
221.24, or any document under subpart C of this part.
    (2) An extension of time to file any other document under subpart B 
of this part may be granted only upon a showing of good cause.
    (i) To request an extension of time, a party must file a motion 
under Sec. 221.35 stating how much additional time is needed and the 
reasons for the request.
    (ii) The party must file the motion before the applicable time 
period expires, unless the party demonstrates extraordinary 
circumstances that justify a delay in filing.
    (iii) The ALJ may grant the extension only if:
    (A) It would not unduly prejudice other parties; and
    (B) It would not delay the decision under Sec. 221.60.